Let's take a look at progress of the new for 2027 attraction at SDC.
Here behind the Lumbercamp Falls you can see they are still working on grading

It's almost like they cannot decide how they want this area's topography to look

Will this become a new connector pathway behind Lumbercamp Falls? We sure hope so

Another look at where they keep carving away at a hill

Looks like more fill gravel has shown up

On the Wildfire side now, here's a look at the new façade and water runoff channel for American Plunge

Water retention pond and new footers for the coming ride

The new façade looks nice.  It will be interesting to see the details they add to it

Here you can see the façade covers the bottom of the American Plunge lift

Retention pool, footers and the new look of American Plunge

One last look at this area.  Fairly obvious that track will be going over this new building

Looking over at PowderKeg and some massive footers

Footers under those black bags.  I am guessing more will go into that gravel area as well

Lots of footers under Wildfire's lift

The footers carve into the hill and then head on down towards a helix in the trees past Wildfire

Appears we have a meeting going on here.  Look at the size of this footers next to them

There's a row of footers next to PowderKeg's first hill (after the launch)

The orange fence is surrounding the footers under Wildfire's lift

Definitely the "Valley of the Coasters"

No footers yet in this helix opening

Probably won't be long though as gravel has started to arrive

Who else excited for this new Mack coaster?