May 12, 2024

Six Flags St. Louis - Joker Update

 


All four footers are now installed for Joker

It also appears that most of the electrical has been run (the tubes are an indicator) which means they are getting closer to being able to pour the concrete slab for the loading area

Here you can see the other two footers, closest to Rookie Racer

Looking at one of the footers and where the concrete slab will soon go

The two footers closest to Thunder River