Time to check back in on the progress at Oasis LOZ. This is the resort peninsula.
The resort has made some vertical progress since our last visit
Not sure what is going on here, but there were busy playing with the dirt on the point of the resort peninsula
Walls be standing and it looks like they are in the process of creating more
Looks like another ride is getting pieced together before being transported over to the park in the staging area near Dog Days
The parking garage is looking more and more complete
It is a pretty impressive looking structure from the road that leads to Dog Days
Apparently it stretches further towards the park as it looks like the next section of the garage is now going up here
Which makes sense, because if you look this whole side of the garage is open
Let's now look at what's going on over on the park peninsula
The station for the ferris wheel is getting closed in with framing
A new structure has popped up here (it's only the roof right now)
The station for the ferris wheel is pretty good sized
Dragon Run peeking over the fence
A good profile shot of Dragon Run. You can see the framing going in on the ferris wheel building
Here you can see how far over the garage will stretch. Those pillars should be the farthest points of the structure
Here's what the resort looks like from this side
Zooming in on the framing in progress
Safety fencing up on Dragon Run
Looks like this helix section will really hug the ground and retaining wall
That's all for this update